In a major step towards early completion of 120 MW Rangit IV Project of JPCL a fully subsidiary of #NHPC, the excavation of balance 2696 m of Head Race Tunnel (out of total 6488 m) completed on 22/07/2024. #hydropower #renewableenergy #nhpclimited @MinOfPower @PIB_India

nhpcltd's tweet image. In a major step towards early completion of 120 MW Rangit IV Project of JPCL a fully subsidiary of #NHPC, the excavation of balance 2696 m of Head Race Tunnel (out of total 6488 m) completed on 22/07/2024.
#hydropower #renewableenergy #nhpclimited @MinOfPower
@PIB_India
nhpcltd's tweet image. In a major step towards early completion of 120 MW Rangit IV Project of JPCL a fully subsidiary of #NHPC, the excavation of balance 2696 m of Head Race Tunnel (out of total 6488 m) completed on 22/07/2024.
#hydropower #renewableenergy #nhpclimited @MinOfPower
@PIB_India

Saurabh Singh gönderiyi yeniden yayınladı

Sh. R.N. Sahoo, SM (Geo), Sh. Saurabh Singh, SM (Civil) & Sh. Pankaj Rawat, DM (Geo) from NHPC participated in 14th Asian Regional Conference of IAEG held at Kuala Lumpur, Malaysia (27th-29th Feb’24) & won Best Speaker Award for the technical paper presentation. #RenewableEnergy

nhpcltd's tweet image. Sh. R.N. Sahoo, SM (Geo), Sh. Saurabh Singh, SM (Civil) & Sh. Pankaj Rawat, DM (Geo) from NHPC participated in 14th Asian Regional Conference of IAEG held at Kuala Lumpur, Malaysia (27th-29th Feb’24) & won Best Speaker Award for the technical paper presentation.
#RenewableEnergy
nhpcltd's tweet image. Sh. R.N. Sahoo, SM (Geo), Sh. Saurabh Singh, SM (Civil) & Sh. Pankaj Rawat, DM (Geo) from NHPC participated in 14th Asian Regional Conference of IAEG held at Kuala Lumpur, Malaysia (27th-29th Feb’24) & won Best Speaker Award for the technical paper presentation.
#RenewableEnergy

Saurabh Singh gönderiyi yeniden yayınladı

The inaugural blast for SFT outlet and the critical 2nd stage river diversion for completion of balance 2 blocks on left bank & Dam HM works at 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary, JPCL was sucessfully done in presence of Sh. R.K. Chaudhary, Dir. (Tech. & Proj.).

nhpcltd's tweet image. The inaugural blast for SFT outlet and the critical 2nd stage river diversion for completion of balance 2 blocks on left bank & Dam HM works at 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary, JPCL was sucessfully done in presence of Sh. R.K. Chaudhary, Dir. (Tech. & Proj.).
nhpcltd's tweet image. The inaugural blast for SFT outlet and the critical 2nd stage river diversion for completion of balance 2 blocks on left bank & Dam HM works at 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary, JPCL was sucessfully done in presence of Sh. R.K. Chaudhary, Dir. (Tech. & Proj.).
nhpcltd's tweet image. The inaugural blast for SFT outlet and the critical 2nd stage river diversion for completion of balance 2 blocks on left bank & Dam HM works at 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary, JPCL was sucessfully done in presence of Sh. R.K. Chaudhary, Dir. (Tech. & Proj.).
nhpcltd's tweet image. The inaugural blast for SFT outlet and the critical 2nd stage river diversion for completion of balance 2 blocks on left bank & Dam HM works at 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary, JPCL was sucessfully done in presence of Sh. R.K. Chaudhary, Dir. (Tech. & Proj.).

Saurabh Singh gönderiyi yeniden yayınladı

In a major step towards 2nd Stage River Diversion for completion of 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary JPCL, the critical Hydro-Mechanical activity of “Erection of 1 no. Spillway Radial Gate in Bay no-4” was completed & trial operation done successfully. #nhpc

nhpcltd's tweet image. In a major step towards 2nd Stage River Diversion for completion of 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary JPCL, the critical Hydro-Mechanical activity of “Erection of 1 no. Spillway Radial Gate in Bay no-4” was completed & trial operation done successfully.
#nhpc
nhpcltd's tweet image. In a major step towards 2nd Stage River Diversion for completion of 120 MW Rangit-IV HEP (Sikkim) of NHPC’s subsidiary JPCL, the critical Hydro-Mechanical activity of “Erection of 1 no. Spillway Radial Gate in Bay no-4” was completed & trial operation done successfully.
#nhpc

Saurabh Singh gönderiyi yeniden yayınladı

Concreting upto Dam top i.e. EL 471 m of Overflow Block 3/Bay 1 was completed at 120 MW Rangit IV HEP of #NHPC’s subsidiary JPCL on 21.8.23. Spillway blocks (Nos. 3/4/5/6) & NOF Blocks (7/8) upto dam top level & deck slab in Spillway (block 5/6) have also been completed.

nhpcltd's tweet image. Concreting upto Dam top i.e. EL 471 m of Overflow Block 3/Bay 1 was completed at 120 MW Rangit IV HEP of #NHPC’s subsidiary JPCL on 21.8.23. Spillway blocks (Nos. 3/4/5/6) & NOF Blocks (7/8) upto dam top level & deck slab in Spillway (block 5/6) have also been completed.

Blessed to be part of this journey.

Major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary, JPCL – June 2023 #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib

nhpcltd's tweet image. Major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary, JPCL – June 2023 #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. Major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary, JPCL – June 2023 #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. Major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary, JPCL – June 2023 #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. Major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary, JPCL – June 2023 #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib


Saurabh Singh gönderiyi yeniden yayınladı

In one of the biggest achievements towards completion of 2000 MW Subansiri Lower HE Project, the Dam top level of EL 210 M has been completed in all the blocks on 29.06.2023. #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib

nhpcltd's tweet image. In one of the biggest achievements towards completion of 2000 MW Subansiri Lower HE Project, the Dam top level of EL 210 M has been completed in all the blocks on 29.06.2023. #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. In one of the biggest achievements towards completion of 2000 MW Subansiri Lower HE Project, the Dam top level of EL 210 M has been completed in all the blocks on 29.06.2023. #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. In one of the biggest achievements towards completion of 2000 MW Subansiri Lower HE Project, the Dam top level of EL 210 M has been completed in all the blocks on 29.06.2023. #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib
nhpcltd's tweet image. In one of the biggest achievements towards completion of 2000 MW Subansiri Lower HE Project, the Dam top level of EL 210 M has been completed in all the blocks on 29.06.2023. #hydropower #nhpclimited #MinOfPower #PIB_India #power_pib

Saurabh Singh gönderiyi yeniden yayınladı

In major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary JPCL, the concreting up to Dam top i.e. EL 471.0m of *Overflow Block no 6/Spillway no 4* has been completed on 31.05.23. #hydropower #RenewableEnergy #nhpclimited

nhpcltd's tweet image. In major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of NHPC’s subsidiary JPCL, the concreting up to Dam top i.e. EL 471.0m  of  *Overflow Block no 6/Spillway no 4*  has been completed on 31.05.23. #hydropower #RenewableEnergy #nhpclimited

Saurabh Singh gönderiyi yeniden yayınladı

In major step towards early completion of balance works of 120MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the balance HRT excavation is now less than 1500m as on 7.5.23 out of total HRT length of 6488m. Progress was made despite adverse geological conditions.

nhpcltd's tweet image. In major step towards early completion of balance works of 120MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the balance HRT excavation is now less than 1500m as on 7.5.23 out of total HRT length of 6488m. Progress was made despite adverse geological conditions.
nhpcltd's tweet image. In major step towards early completion of balance works of 120MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the balance HRT excavation is now less than 1500m as on 7.5.23 out of total HRT length of 6488m. Progress was made despite adverse geological conditions.

Saurabh Singh gönderiyi yeniden yayınladı

Major achievements at RANGIT- IV HEP (120 MW), Sikkim- April 2023 #hydropower #RenewableEnergy #nhpclimited @MinOfPower @PIB_India @power_pib

nhpcltd's tweet image. Major achievements at  RANGIT- IV HEP (120 MW), Sikkim- April 2023 #hydropower #RenewableEnergy #nhpclimited @MinOfPower @PIB_India @power_pib
nhpcltd's tweet image. Major achievements at  RANGIT- IV HEP (120 MW), Sikkim- April 2023 #hydropower #RenewableEnergy #nhpclimited @MinOfPower @PIB_India @power_pib
nhpcltd's tweet image. Major achievements at  RANGIT- IV HEP (120 MW), Sikkim- April 2023 #hydropower #RenewableEnergy #nhpclimited @MinOfPower @PIB_India @power_pib
nhpcltd's tweet image. Major achievements at  RANGIT- IV HEP (120 MW), Sikkim- April 2023 #hydropower #RenewableEnergy #nhpclimited @MinOfPower @PIB_India @power_pib

Saurabh Singh gönderiyi yeniden yayınladı

In major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the construction milestones of 1000 m excavation of HRT & 500 m Overt lining of HRT were completed on 28.02.2023 despite adverse geological conditions.

nhpcltd's tweet image. In major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the construction milestones of 1000 m excavation of HRT & 500 m Overt lining of HRT were completed on 28.02.2023 despite adverse geological conditions.
nhpcltd's tweet image. In major steps towards early completion of balance works of 120 MW Rangit IV Project (Sikkim) of #NHPC’s subsidiary JPCL, the construction milestones of 1000 m excavation of HRT & 500 m Overt lining of HRT were completed on 28.02.2023 despite adverse geological conditions.

Saurabh Singh gönderiyi yeniden yayınladı

In a major step towards timely completion of balance works of 120 MW Rangit-IV HEP (Sikkim) of JPCL (NHPC's subsidiary), twin inaugural blast taken at Branch SFT#1 & Branch SFT#3 simultaneously in august presence of Dir.(Projects) Sh. Biswajit Basu & CEO(JPCL). #NHPC @MinOfPower

nhpcltd's tweet image. In a major step towards timely completion of balance works of 120 MW Rangit-IV HEP (Sikkim) of JPCL (NHPC's subsidiary), twin inaugural blast taken at Branch SFT#1 & Branch SFT#3 simultaneously in august presence of Dir.(Projects) Sh. Biswajit Basu & CEO(JPCL).
#NHPC @MinOfPower

Saurabh Singh gönderiyi yeniden yayınladı

Construction activities are going in full swing on 24 x 7 basis towards timely completion of 120 MW Rangit- IV HEP (Sikkim) of JPCL (a wholly owned subsidiary of NHPC). Night view of concreting at Dam site of the project. #NHPC #Hydropower @MinOfPower @power_pib


Saurabh Singh gönderiyi yeniden yayınladı

In major steps towards completing 120MW Rangit-IV HEP(Sikkim) of JPCL(NHPC's subsidiary), concreting of 1st lift of trunnion beam of Spillway 1 (4th&last) & Installation of Radial Gate Sill Beam in Bay 4(Block6) began on 22.1.23 in presence of Sh.Biswajit Basu,Dir(Projects),NHPC.

nhpcltd's tweet image. In major steps towards completing 120MW Rangit-IV HEP(Sikkim) of JPCL(NHPC's subsidiary), concreting of 1st lift of trunnion beam of Spillway 1 (4th&last) & Installation of Radial Gate Sill Beam in Bay 4(Block6) began on 22.1.23 in presence of Sh.Biswajit Basu,Dir(Projects),NHPC.

Saurabh Singh gönderiyi yeniden yayınladı

NHPC made major achievements at 120 MW Rangit-IV Hydroelectric Project (Sikkim) during December 2022. #NHPC #Hydropower @MinOfPower @power_pib @PIB_India @PIBGangtok

nhpcltd's tweet image. NHPC made major achievements at 120 MW Rangit-IV Hydroelectric Project (Sikkim) during December 2022.
#NHPC #Hydropower 
@MinOfPower @power_pib @PIB_India @PIBGangtok
nhpcltd's tweet image. NHPC made major achievements at 120 MW Rangit-IV Hydroelectric Project (Sikkim) during December 2022.
#NHPC #Hydropower 
@MinOfPower @power_pib @PIB_India @PIBGangtok
nhpcltd's tweet image. NHPC made major achievements at 120 MW Rangit-IV Hydroelectric Project (Sikkim) during December 2022.
#NHPC #Hydropower 
@MinOfPower @power_pib @PIB_India @PIBGangtok
nhpcltd's tweet image. NHPC made major achievements at 120 MW Rangit-IV Hydroelectric Project (Sikkim) during December 2022.
#NHPC #Hydropower 
@MinOfPower @power_pib @PIB_India @PIBGangtok

Saurabh Singh gönderiyi yeniden yayınladı

In major steps towards completing 120 MW Rangit-IV HEP (Sikkim) of #NHPC's subsidiary JPCL, Day-lighting was achieved in 5.5 m dia Vertical Pressure Shaft & at dam site, Monolithic Concreting for breast wall including trunion beam began in Bay 6 (Spillway Bay 4) on 12.12.22.

nhpcltd's tweet image. In major steps towards completing 120 MW Rangit-IV HEP (Sikkim) of #NHPC's subsidiary JPCL, Day-lighting was achieved in 5.5 m dia Vertical Pressure Shaft & at dam site, Monolithic Concreting for breast wall including trunion beam began in Bay 6 (Spillway Bay 4) on 12.12.22.
nhpcltd's tweet image. In major steps towards completing 120 MW Rangit-IV HEP (Sikkim) of #NHPC's subsidiary JPCL, Day-lighting was achieved in 5.5 m dia Vertical Pressure Shaft & at dam site, Monolithic Concreting for breast wall including trunion beam began in Bay 6 (Spillway Bay 4) on 12.12.22.
nhpcltd's tweet image. In major steps towards completing 120 MW Rangit-IV HEP (Sikkim) of #NHPC's subsidiary JPCL, Day-lighting was achieved in 5.5 m dia Vertical Pressure Shaft & at dam site, Monolithic Concreting for breast wall including trunion beam began in Bay 6 (Spillway Bay 4) on 12.12.22.

Saurabh Singh gönderiyi yeniden yayınladı

In a major step towards completion of NHPC's 2000 MW Subansiri Lower HEP (Assam/Arunachal Pradesh), the civil works of Intake Structure No. 5 of Head Race Tunnel was completed on 21.11.22. #Hydropower #nhpclimited @raghurajmr @MinOfPower @power_pib @PIB_India

nhpcltd's tweet image. In a major step towards completion of NHPC's 2000 MW Subansiri Lower HEP (Assam/Arunachal Pradesh), the civil works of Intake Structure No. 5 of Head Race Tunnel was completed on 21.11.22.
#Hydropower #nhpclimited @raghurajmr @MinOfPower @power_pib @PIB_India
nhpcltd's tweet image. In a major step towards completion of NHPC's 2000 MW Subansiri Lower HEP (Assam/Arunachal Pradesh), the civil works of Intake Structure No. 5 of Head Race Tunnel was completed on 21.11.22.
#Hydropower #nhpclimited @raghurajmr @MinOfPower @power_pib @PIB_India

Saurabh Singh gönderiyi yeniden yayınladı

In a major step, 120 MW Rangit IV HEP, Sikkim of JPCL (#NHPC’s Subsidiary) achieved 695 mtrs HRT excavation (Out of total balance 2694 mtr) on 18.11.22 despite challenges/adverse geological conditions. Balance excavation is now less than 2 Km. @MinOfPower @raghurajmr @power_pib

nhpcltd's tweet image. In a major step, 120 MW Rangit IV HEP, Sikkim of JPCL (#NHPC’s Subsidiary) achieved 695 mtrs HRT excavation (Out of total balance 2694 mtr) on 18.11.22 despite challenges/adverse geological conditions. Balance excavation is now less than 2 Km.
@MinOfPower @raghurajmr @power_pib
nhpcltd's tweet image. In a major step, 120 MW Rangit IV HEP, Sikkim of JPCL (#NHPC’s Subsidiary) achieved 695 mtrs HRT excavation (Out of total balance 2694 mtr) on 18.11.22 despite challenges/adverse geological conditions. Balance excavation is now less than 2 Km.
@MinOfPower @raghurajmr @power_pib
nhpcltd's tweet image. In a major step, 120 MW Rangit IV HEP, Sikkim of JPCL (#NHPC’s Subsidiary) achieved 695 mtrs HRT excavation (Out of total balance 2694 mtr) on 18.11.22 despite challenges/adverse geological conditions. Balance excavation is now less than 2 Km.
@MinOfPower @raghurajmr @power_pib
nhpcltd's tweet image. In a major step, 120 MW Rangit IV HEP, Sikkim of JPCL (#NHPC’s Subsidiary) achieved 695 mtrs HRT excavation (Out of total balance 2694 mtr) on 18.11.22 despite challenges/adverse geological conditions. Balance excavation is now less than 2 Km.
@MinOfPower @raghurajmr @power_pib

Saurabh Singh gönderiyi yeniden yayınladı

In another critical development towards timely completion of 120 MW Rangit-IV HEP (Sikkim) of JPCL (NHPC's fully owned subsidiary), Backfill Concreting of steel lined Surge Shaft started on 18.11.22 in presence of CEO, JPCL. #NHPC #Hydropower @MinOfPower @raghurajmr @power_pib

nhpcltd's tweet image. In another critical development towards timely completion of 120 MW Rangit-IV HEP (Sikkim) of JPCL (NHPC's fully owned subsidiary), Backfill Concreting of steel lined Surge Shaft started on 18.11.22 in presence of CEO, JPCL.
#NHPC #Hydropower 